Entergy: Less than 5,200 without power on Tuesday

Posted at 11:35 AM, Jul 16, 2019
and last updated 2019-07-16 12:35:25-04

Entergy says that less than 5,200 customers remain without power on Tuesday. 441 of those customers are in Acadiana.

Crews worked overnight in parishes across Louisiana to restore power to customers effected by Hurricane Barry.

Restoration efforts are expected to continue tonight in the hardest hit areas of Baton Rouge, Lafourche and Terrebonne parishes. Entergy says that customers in those areas should be back on line by Wednesday, July 17.

As of Tuesday, July 16, over 4,000 Entergy workers had restored power to more than 325,590 customers.

Most parishes are expected to have a majority of Entergy customers restored overnight on Tuesday, July 16.

Entergy has provided a breakdown by parish of those customers still affected by outages.

East Baton Rouge Parish
Number of outages as of 8 a.m.: 951
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 10 p.m. with the remaining customers being restored Wednesday, July 17.

West Baton Rouge Parish
Number of outages as of 8 a.m.: 75
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 10 p.m. with the remaining customers being restored Wednesday, July 17.

Lafayette Parish
Number of outages as of 8 a.m.: 11
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 6 p.m. with the remaining customers being restored Wednesday, July 17.

Acadia Parish
Number of outages as of 8 a.m.: 20
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 6 p.m. with the remaining customers being restored Wednesday, July 17.

Iberia Parish
Number of outages as of 8 a.m.: 179
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 6 p.m. with the remaining customers being restored Wednesday, July 17.

St. Martin Parish
Number of outages as of 8 a.m.: 145
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 6 p.m. with the remaining customers being restored Wednesday, July 17.

Vermilion Parish
Number of outages as of 8 a.m.: 86
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 6 p.m. with the remaining customers being restored Wednesday, July 17.

Ascension Parish
Number of outages as of 8 a.m.: 78
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 10 p.m. with the remaining customers being restored Wednesday, July 17.

Assumption Parish
Number of outages as of 8 a.m.: 378
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 10 p.m. with the remaining customers being restored Wednesday, July 17.

St. James Parish
Number of outages as of 8 a.m.: 53
Percentage of damage assessments complete: 100%
Estimated restoration for area will be Tuesday, July 16 at 12 p.m.

St. John the Baptist Parish
Number of outages as of 8 a.m.: 1
Percentage of damage assessments complete: 100%
Estimated restoration for area will be Tuesday, July 16 at 12 p.m.

Terrebonne Parish
Number of outages as of 8 a.m.: 1,933
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 10 p.m. with the remaining customers being restored Wednesday, July 17.

Lafourche Parish
Number of outages as of 8 a.m.: 473
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 10 p.m. with the remaining customers being restored Wednesday, July 17.

Plaquemines Parish
Number of outages as of 8 a.m.: 45
Percentage of damage assessments complete: 100%
The majority of customers will be restored on Tuesday, July 16 by 10 p.m. with the remaining customers being restored Wednesday, July 17.