Jeff Davis Electric will have a scheduled outage on Wednesday, November 12, 2025, starting at 8 AM at the Fulton Substation.
This outage is required to connect this substation to grid power using the newly constructed 230 kV line, removing the need for generator power.
The outage is estimated to last 10 hours.
Members of Cameron, Marshall St., W. Creole Hwy., and Trosclair Rd. will be affected by the outage.